Project Description

S.R. 0079, Section C10

Next  Project

Previous Project

S.R. 0079, Section C10 - Resurfacing - Exit 6 - U.S. 19 - Looking West

S.R. 0079  Section C10 - Exit 6 - U.S. 19 - Looking North

More Project Aerial Photos

S.R. 0079, Section C10

Washington County, PA

Construction inspection and documentation services for reconstructing approximately 7.9 miles of Interstate 79 just north of the Marianna Interchange to the bridge carrying Route 40 over Interstate 79.  Also included is the interchange at Lone Pine which involves extending the on and off ramps and resurfacing the Laboratory Interchange.  Original concrete was laid in the 1960's.  Five bridges will also be replaced.  One of the bridges carries Interstate 79 over Weaver Run Road (State Route 2006) and the other carries Interstate 79 over State Route 19. 

Client:  PENNDOT District 12-0

             Uniontown,  PA

Project Cost:  $26.0M

Completion Date:  2002

 

 

Project Location Map
Reconstruction of existing pavement with superpave bituminous pavement courses including a wearing course, binder course, base course, and subbase.  Construction of two dual simple span composite prestressed concrete spread box beam bridges, rehabilitation of a simple span prestressed concrete adjacent box beam bridge and the miscellaneous construction of drainage, guide rail, paved shoulders, signing and pavement markings

 

  T. W. CONSULTANTS, INCORPORATED

Engineers and Planners
5500 Corporate Drive ·  Suite 300  ·  Pittsburgh, PA  ·  15237
Phone: (412) 369-7500  ·  Fax: (412) 369-7964 

Copyright © 2000 T.W. CONSULTANTS INCORPORATED

  All rights reserved.